Sterlitamak TPP is a thermal power plant ( cogeneration plant ) located in the city of Sterlitamak in the Republic of Bashkortostan of the Russian Federation. It is part of LLC Bashkir Generating Company , a subsidiary of PJSC Inter RAO .
| Sterlitamak TPP | |
|---|---|
| A country | |
| Location | Sterlitamak |
| Owner | Bashkir Generation Company |
| Status | acting |
| Commissioning | 1957 |
| Main characteristics | |
| Electric power, MW | 320 MW (2019) |
| Thermal power | 1539 Gcal / h (2019) |
| Equipment specifications | |
| Primary fuel | natural gas |
| On the map | |
The Sterlitamak TPP supplies electric energy and power to the wholesale market of electric energy and power . It is the main source of thermal energy for the district heating system of Sterlitamak.
Content
- 1 History
- 2 Description
- 3 notes
- 4 Literature
- 5 Links
History
The start of the first turbine unit of the Sterlitamak TPP took place in September 1957. In December 1967, the ninth turbine unit with a capacity of 100 MW was put into commercial operation - the largest heating turbine in the republic at that time [1] .
During the reform of the electric power industry in Russia, the Sterlitamak TPP was separated from Bashkirenergo into LLC Bashkir Generating Company , which was included in the perimeter of Inter RAO Holding in 2012 [2] .
Description
The Bashkir energy system operates as part of the Ural energy system . At the beginning of 2015, the installed electric capacity of the Sterlitamak TPP is 345 MW or 7% of the total capacity of the regionβs power plants. Electricity generation in 2014 amounted to 1589.9 million kWβ h [3] .
Sterlitamak TPP operates in the mode of combined generation of electric and thermal energy. It is the main source of thermal energy for the district heating system of Sterlitamak. In 2014, the supply of thermal energy amounted to 1,799.5 thousand Gcal, including 730.1 thousand Gcal - steam to industrial consumers [4] .
The thermal scheme of the thermal power station is cross-linked to a fresh steam pressure of 9.0 and 13.0 MPa. The main equipment includes [4] :
- energy (steam) boilers;
- six turbo units :
- PT-25-90 / 10;
- 2 x PT-60-130 / 13;
- 2 x P-50-130 / 13;
- T-100-130.
The main fuel used is natural gas [4] .
Notes
- β Olga Goryunova. Sterlitamak TPP - 50 years . Bashinform (December 17, 2007).
- β Bashkir Encyclopedia, 2009 .
- β Scheme and program for the prospective development of the electric power industry of the Republic of Bashkortostan for the period 2016-2020: Volume 1, Book 1 . Ministry of Industry and Innovation Policy of the Republic of Bashkortostan.
- β 1 2 3 Scheme and program for the prospective development of the electric power industry of the Republic of Bashkortostan for the period 2016-2020: Volume 4 . Ministry of Industry and Innovation Policy of the Republic of Bashkortostan.
Literature
- Sterlitamak TPP // Bashkir Encyclopedia / Ch. ed. M.A. Ilgamov . - Ufa : Bashkir Encyclopedia , 2009.- T. 5: P - S. - 576 p.
Links
- Sterlitamak TPP . LLC "Bashkir Generation Company".