OPAL is an onshore continuation of the Nord Stream gas pipeline through Germany , delivering gas from Russia to the EU countries , bypassing transit countries [2] . It is one of the largest infrastructure energy projects in Germany.
| Opal | |
|---|---|
| Location | |
| A country | |
| general information | |
| Operator | and |
| Technical information | |
| Length | |
| Supply pipe | Nord Stream |
| Bends | Gazelle |
The gas pipeline runs from Greifswald to Olbernhau , connecting the Trans-Baltic Nord Stream with the existing gas transmission networks in Europe [3] . The construction was completed in 2011 , and already in August 2011 was connected with the Nord Stream gas pipeline. [four]
The gas pipeline project was developed by the German company OPAL NEL TRANSPORT GmbH, in the operational management of which it is currently located, which, in turn, is a subsidiary of .
Specifications
The length of the pipeline is 470 kilometers. The diameter of the pipes is 1.4 meters.
The throughput is 36 billion cubic meters of gas per year [5] .
The compressor station is located in Radeland ( Brandenburg ) and is built on Siemens equipment. [6]
The cost of the pipeline is about 1 billion euros .
The gas pipeline runs from n.p. Lubmin , near Greifswald, to Olbernhau . It connects the Nord Stream pipeline with JAGAL (Yamal - Europe) and further with STEGAL (Central European Transit System) on the other hand. On the German-Czech border, the OPAL extension is the Gazelle gas pipeline, which runs through the Czech Republic and re- enters Germany, connecting with the MEGAL gas pipeline. [7]
Gazelle Gas Pipeline
The continuation in the Czech Republic is the Gazela gas pipeline . A 166-km gas pipeline starts from the village of Brandov on the Czech-German border . In transit through the Czech Republic passes to Bavaria , where it connects to the German gas transportation system.
Construction began in October 2010 and was commissioned in January 2013 . Its capacity is 30 billion m³, which is three times higher than the annual gas consumption in the Czech Republic. The possibility of reverse operation is also provided [8] . The cost amounted to 400 million euros, the investor was NET4GAS .
Operation
Germany and Russia are currently trying to remove the OPAL gas pipeline from the EU’s Third Energy Package , according to which 50% of the gas pipeline should belong to third parties, which Russia fundamentally cannot agree to because Gazprom is the only natural gas supplier Nord Stream ”, filling in turn OPAL. [9]
Efficient use of OPAL facilities would mean a decrease in the role of Ukraine as a transit country, and the commissioning of the Nord Stream 2 and Turkish Stream pipelines would mean a complete cessation of transit through its territory.
On October 28, 2016, information appeared on the achievement of a solution to this issue in favor of the withdrawal of the OPAL gas pipeline from the norms of the third energy package until 2033. [10] [11] .
On December 23, 2016, the European Court suspended the decision of the European Commission on the access of Russian Gazprom to the OPAL pipeline [12] , as an interim measure for the period of the trial. The decision was made at the suit of the Polish company PGNiG and the Polish government [13] .
In June 2017, the European Court refused to admit Gazprom as a third party in the case, and in July of the same year removed the interim measure established on December 23, 2016 [14] .
On August 3, 2017, it was reported that after the ban on the use of 40% of the OPAL pipeline’s capacities was lifted, Gazprom increased transit through it, the pipeline’s load increased by more than a quarter due to a reduction in gas transit through Ukraine. [15]
EUGAL
| External video files | |
|---|---|
| Construction EUGAL , 2019 | |
As an onshore continuation of the Nord Stream 2 gas pipeline, the OPAL doubler, the EUGAL gas pipeline, is under construction. [16] The differences are in a greater capacity equal to the total capacity of the OPAL and NEL gas pipelines - 55 billion cubic meters per year and at another delivery point on the Czech border, located in Deutschendorf [17] .
Continuation of EUGAL in the Czech Republic is the NET4GAS company’s Capacity4Gas gas pipeline under construction (parallel to the existing Gazelle gas pipeline) [18] , with phased commissioning in 2019 and 2021. [19] The diameter of Capacity4Gas will be 1,400 mm; an increase in throughput will be achieved through the construction of the Gora-Swate-Katerini compressor station.
Notes
- ↑ http://www.lbtg.de/de/node/31
- ↑ Russia got the right to use the OPAL pipeline to 100% // Eurasian wave
- ↑ Lochner, Stefan; Bothe, David. From Russia with Gas An analysis of the Nord Stream pipeline's impact on the European Gas Transmission System with the Tiger-Model (Eng.) // EWI Working Paper: journal. - Institute of Energy Economics at the University of Cologne, 2007. - September ( no. 07.02 ). (inaccessible link)
- ↑ Blau, John . Nord Stream pipeline now connected to German link (August 26, 2011). Date of treatment September 10, 2011.
- ↑ Opal Gas Pipeline Archived October 20, 2014. / Kommersant Directory
- ↑ Siemens wins Baltic pipeline compressor order , Offshore , PennWell Corporation (March 17, 2010). Archived January 3, 2011. Date of treatment March 18, 2010.
- ↑ Markéta Hulpachová . RWE plans new pipeline , The Prague Post (May 23, 2007). Archived June 1, 2007. Date of treatment November 24, 2007.
- ↑ Gazel gas trunkline commissioned in the Czech Republic
- ↑ Miller: EC may allow the use of the Opal gas pipeline // RIA Novosti, May 2014
- ↑ The EC confirmed the conclusion of OPAL from the norms of the Third Energy Package
- ↑ Gas markets: Commission reinforces market conditions in revised exemption decision on OPAL pipeline // lenta.ru
- ↑ European Union Court bans Gazprom’s “harmful” access to OPAL pipeline // December 27, 2016
- ↑ EU Court does not support Poland in Opal gas pipeline dispute
- ↑ The EU Court did not support Poland in the dispute over the Opal gas pipeline // RIA
- ↑ Russian gas goes through OPAL bypassing Ukraine (Russian) , IA REGNUM (August 3, 2017). Date of treatment August 3, 2017.
- ↑ [1] (inaccessible link) // eugal.de
- ↑ Wintershall: the inclusion of EUGAL in the German gas transportation system development plan is the key to the payback of the project . Interfax-Azerbaijan (April 4, 2019). Date of treatment April 5, 2019.
- ↑ https://www.net4gas.cz/en/transmission-system/
- ↑ https://www.net4gas.cz/en/projects/capacity4gas-project/