NARM - a floating road collapsible bridge. Designed for bridge and ferry crossings over medium and large water barriers on military roads.
| NARM | |
|---|---|
| Type of construction | Pontoon |
| Material | Steel |
| Application area | Medium and large water barriers |
| Manufacturer | |
| Specifications | |
| Carrying capacity | 60 t |
| Bridge length | 226.76 m |
| Allowable Speed | 2.5 m / s |
| Roadway Width | 6.8 m |
| Guidance time | 2 hours |
| Payment | 148 people |
| Lanes | 2 pcs. |
| Allowable Speed | 30 km / h |
Content
Technical Description
NARM is assembled from folding double-pont links that combine the functions of floating supports, spans and the roadway. The adjacency of the bridge to the coast is arranged from coastal links.
The links are transported on KAMAZ 5410 road trains with the OdAZ -9370 semi-trailer. The property is transported partly on links or in special containers on the platforms of road trains.
Unloading the links to the water is carried out by self-unloading (rolling on the rollers of the semi-trailer) or using cranes. The links are laid out by a crane: the sling is hooked to the earring of the upper pontoon, it is lifted until the pontoon turning on the hinges “rolls over”, after which it is gently lowered until the link is fully opened. Folding is done in the same way.
The NARM is guided by towing and motor boats. For the passage of ships from the line of the bridge, a section of several links is removed (lead-out section). The extreme links remaining in the bridge line (access links) are fixed by the upper and lower anchors.
If the material part of the bridge is not enough to cover the width of the river, it is possible to build combined bridges from Narm and PMP , as well as from Narm and Marm .
Report Card
- river double-pont links - 40 pcs .;
- coastal links - 8 pcs.;
- a set of additional equipment for a semi-trailer road train for transporting links - 48 pcs .;
- containers for transportation of removable tooling of links, auxiliary equipment and spare parts - 5 pcs .;
- set of removable equipment, auxiliary equipment and spare parts - 1 pc.
Characteristics of Ferries Collected from the Material Set
- The number of collected ferries with a carrying capacity of up to 90 tons - 4 pcs.
- Assembly time of ferries of various carrying capacities, min:
- 40 tons with a crew of 14 people - 17 min;
- 60 tons for 17 people - 21 min;
- 90 tons for 23 people - 30 min.
See also
- Pontoon bridge
Literature
- Floating road collapsible bridge (NARM). - M .: Military Publishing House, 1993. - 176 p.
- I. V. Bursevich, V. I. Pugachev and others. Military bridge training. - M .: Military Publishing House, 1992. - 328 p.
- Technical facilities of the rear services. Directory. The rear headquarters of the USSR Armed Forces. M .: Military Publishing House of the Ministry of Defense of the USSR, 1979.
- Logistics support equipment. Directory. The rear headquarters of the Armed Forces of the Russian Federation. M .: Military Publishing, 2003.