Yushkozero hydroelectric power station - hydroelectric station on the Kem river near the Yushkozero station in Karelia . Included in the Kem cascade hydroelectric station.
| Yushkozerskaya HPP | |
|---|---|
![]() | |
| A country | |
| River | Kem |
| Cascade | Kem |
| Owner | TGK-1 |
| Status | acting |
| Year of construction | 1971 |
| Years of entry units | 1980 |
| Main characteristics | |
| Annual electricity generation, mln kWh | 79 |
| Variety of power station | dam-diversion |
| Calculated head , m | 8.5 |
| Electric power, MW | 18 |
| Characteristics of the equipment | |
| Turbine type | rotary lobed |
| Number and brand of turbines | 2 × PL 20/661-B-500 |
| Flow through turbines, m³ / s | 2 × 125 |
| Number and brand of generators | 2 × HCV 700 / 69-64 |
| Generator power, MW | 2 × 9 |
| Main facilities | |
| Dam type | earthen; concrete spillway; levees |
| Dam height, m | 11.5 |
| Dam length, m | 133; 26; 345 |
| Gateway | timber tray |
| Open switchgear | 110 kV (2 × 16 MVA) |
| On the map | |
General Information
The construction of the hydropower plant began in 1971 , ended in 1982. The launch of the hydropower plant was carried out on March 13, 1980 .
The composition of hydroelectric facilities:
- spillway concrete dam 26 m long;
- an earthen channel dam 133 m long and the highest 11.5 m high;
- right bank dam 160 m long;
- left bank dam length 185 m;
- supply channel 480 m long;
- discharge channel 180 m long;
- near the dam of the hydroelectric station with a length of 72 m.
The capacity of the hydroelectric power station is 18 MW, the average annual output is 79 million kWh . In the building of the hydroelectric power station there are 2 rotary-blade hydraulic units of 9 MW each, operating at a design head of 8.5 m.
The supporting structures of the hydroelectric power station (the length of the pressure front is 270 m) form the Yushkozersky reservoir , which includes the lakes Upper , Middle and Lower Kuyto . The reservoir area is 654 km², the total and useful capacity is 1.566 and 1.254 km³. When creating the reservoir, 490 hectares of farmland were flooded, 491 buildings were moved. The reservoir carries out long-term flow regulation, increasing the production of the underlying HPPs of the cascade.
HPP was designed by the Institute " Lengidroproekt ".
The Yushkozerskaya HPP is part of TGC-1 OJSC.