TPP-20

TPP-20 is a power plant in Moscow , part of Mosenergo . Located in the South-Western district on the territory of the Academic region .

TPP-20
Thermal Power Station-20.jpg
A country Russia
LocationMoscow , Vavilova street , 13
OwnerPJSC Mosenergo
Statusacting
CommissioningApril 2, 1952
Main characteristics
Electric power, MW1110 MW
Thermal power2557 Gcal / h
Equipment specifications
Primary fuelnatural gas
Reserve fuelfuel oil , diesel fuel
other information
Sitewww.mosenergo.ru
On the map

Content

Key performance indicators

Data as of January 1, 2009 :

  • Installed electric power - 730 MW
  • Electricity generation (per year) - 4232.1 million kWh
  • Installed heat capacity - 2400 Gcal / h
  • Heat energy output from collectors (per year) - 4500.7 thousand Gcal

The CHPP-20 provides electric and thermal energy to the areas of Academic, Gagarinsky , Lomonosovsky , Obruchevsky , Donskoy , Dorogomilovo , Danilovsky , as well as Yakimanka , Zyuzino , Kotlovka , Konkovo , Cheryomushki and Zamoskvorechye .

The main and reserve fuel is natural gas , emergency fuel is fuel oil .

History

The construction of one of the central power plants of the Moscow power system (the original name is Kalugskaya TPP ) began in 1939 . On April 2, 1952, the CHPP began supplying consumers with thermal energy, and in October of that year - electric.

In the 1960s , CHPP-20 became a pioneer in the development of prototypes of the cogeneration turbine T-100-130 of the Ural Turbo-Motor Plant . In order to meet the needs of the areas closest to TPP-20 with heat and electricity in 1963–66 , four T-100-130 turbines with five TP-87 coal-fired boilers were commissioned at the power plant. Eight water boilers (PTV-100 and PTVM-100) were put into operation to cover the peak heat load. In 1969, CHPP-20 switched to burning fuel oil as an emergency type of fuel. Since 1994, the station is listed in the gas-oil category.

In order to increase the efficiency of the power plant, its technical improvement is constantly carried out. Over the 50 years of operation, the CHPP-20 turbine fleet has been updated by 90%, technical, economic and environmental indicators of equipment have been improved, boiler efficiency has been increased by an average of 3%. Due to the introduction of low-toxic burners, emissions of toxic gases in the atmosphere in 2008 were reduced by 26% . In 2005-2008, by 5% reduced specific fuel consumption for electricity supply. The excessive consumption of fuel due to deviations of primary technical and economic indicators is reduced by 3.6%. At present, the equipment of the CHPP-20 is equipped with modern means of monitoring and control of technological processes.

As part of the energy saving program, a frequency-controlled drive (VFD) of phosphate pumps and fluid couplings was introduced on the II lift network pumps and power electric pumps, which significantly increased the reliability of the equipment and reduced power consumption for own needs.

New Construction

In accordance with the medium-term program for the development and technical re-equipment of existing power plants of Mosenergo OJSC, a two-shaft cogeneration power unit PGU-420 was built at TPP-20 in 2011-2015. The general contractor for the construction of the facility was OJSC MEC Mosenergo [1] .

Key parameters of the new power unit:

  • Installed electric power - 420 MW.
  • Installed heat capacity - 220 Gcal / h.
  • The main fuel is natural gas.
  • The efficiency of CCGT-420 (in condensation mode) is over 58%.

The power island of the power unit (gas and steam turbines with synchronous generators) was supplied by Siemens.

The manufacturer and supplier of the waste heat boiler is EMAlliance OJSC.

CCGT-420 was commissioned on December 22, 2015 [2] [3] .

Facts

  • From 1974 to 1985, a Russian nationalist, now a monk of the CPI Rafaila (Prokopyeva) Alexander Barkashov , worked as an electrician at this CHPP.

In the movie

  • The film " Young Green ." In the scene of the meeting of the protagonist of the film performed by Oleg Tabakov with his teacher, who was filming on Television Street , the cooling towers of the TPP-20 are visible.
  • The film “ Urban Romance ” - pipes and cooling towers of TPP-20 appear as a background in several scenes.
  • The film " Sunflowers ". In the scene where the main character performed by Sophia Loren, goes to the station and gets on the train, CHP-20 is shown.
  • CHP-20 appears in the film A. Tarkovsky "Stalker" . In the final scene, Stalker, his wife and daughter walk along the shore of the ash pond. In the background, the CHPP-20 creates an industrial landscape. Of the wells sticking out of the water, the Chura River flowing underground. CHP-20 is also visible in the open door of the zucchini, where the heroes sit before and after going to the Zone.
  • The film " 34th ambulance ." In the initial scenes, the train departed from the Kiev station, and passes through the Kanatchikovo station. In the background are visible pipes and structures of the CHPP-20.
  • The film " Guys! .. ". The heroes boarded the bus with the inscription "Nickel" was filmed near the house with the address Bolshaya Cheryomushkinskaya Street , Building 2, and in the background you can see the building of the boiler-turbine department No. 2, cooling towers and pipes of TPP-20.

List of main equipment

UnitType ofManufactureramountCommissioningMain characteristicsSources
ParameterValue
Steam turbine equipment
Steam boilerTP-170Taganrog boiler plant " Red Kotelshchik "31952
1954
Fuelgas fuel oil[four]
Performance170 t / h
Steam parameters100 kgf / cm 2 , 510 ° С
Steam boilerTP-230Taganrog boiler plant " Red Kotelshchik "31955
1958
Fuelgas fuel oil[four]
Performance230 t / h
Steam parameters100 kgf / cm 2 , 510 ° С
Steam boilerE-500-13.8-560GM (TP-80M)Taganrog boiler plant " Red Kotelshchik "one1963Fuelgas fuel oil[four]
Performance500 t / h
Steam parameters140 kgf / cm 2 , 560 ° С
Steam boilerE-500 (TP-87M)Taganrog boiler plant " Red Kotelshchik "21963
1964
Fuelgas fuel oil[four]
Performance500 t / h
Steam parameters140 kgf / cm 2 , 560 ° С
Steam boilerTP-87Czechoslovakia21965Fuelgas fuel oil[four]
Performance420 t / h
Steam parameters140 kgf / cm 2 , 560 ° С
Steam boilerTGM-84BTaganrog boiler plant " Red Kotelshchik "one1970 yearFuelgas fuel oil[four]
Performance420 t / h
Steam parameters140 kgf / cm 2 , 560 ° С
Steam turbinePT-30-90Leningrad Metal Plant21953
1997 year
Installed capacity30 MW[four]
Thermal load60 Gcal / h
Steam turbinePT-65-90 / 13Leningrad Metal Plantone1987 yearInstalled capacity65 MW[four]
Thermal load127 Gcal / h
Steam turbineT-110 / 120-130Ural Turbine Plantfour1987 year
1988 year
1989 year
1998 year
Installed capacity110 MW[four]
Thermal load175 Gcal / h
Steam turbineT-100-130Ural Turbine Plantone1970 year
Installed capacity100 MW[four]
Thermal load160 Gcal / h
Water-heating equipment
Hot water boilerPTV-100Biysk boiler plant31959-1960Fuelgas[four]
Thermal power100 Gcal / h
Hot water boilerPTVM-100Biysk boiler plant
Dorogobuzh boiler plant
five1961-1966Fuelgas[four]
Thermal power100 Gcal / h
Hot water boilerPTVM-180Dorogobuzh boiler plant21971Fuelgas[four]
Thermal power180 Gcal / h
Equipment for combined cycle plant PGU-420T
Gas turbineSGT5-4000FSiemensone2015 yearFuelgas , diesel[4] [5]
Installed capacity281 MW
t exhaust579 ° C
Waste heat boilerEMA-024-KUTaganrog boiler plant " Red Kotelshchik "one2015 year
Performance264 t / h[four]
Steam parameters125.3 kgf / cm 2 , 538 ° C
Thermal power0 Gcal / h
Steam turbineSST5-5000Siemensone2015 yearInstalled capacity137 MW[four]
Thermal load220 Gcal / h

See also

  • List of thermal power plants in Russia (installed capacity of more than 25 MW)

Notes

  1. ↑ Mosenergo - Projects (neopr.) (Inaccessible link) . Date of treatment December 3, 2014. Archived December 29, 2014.
  2. ↑ News
  3. ↑ http://so-ups.ru/index.php?id=odu_center_news_view&no_cache=1&tx_ttnews [tt_news] = 7966
  4. ↑ 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 The heat supply scheme of the city of Moscow for the period until 2032 (neopr.) . The official portal of the Mayor and the Government of Moscow . Date of treatment November 6, 2018.
  5. ↑ SGT5-4000F gas turbine (neopr.) . www.energy.siemens.com . Date of treatment November 4, 2018.

Links

Source - https://ru.wikipedia.org/w/index.php?title= TPP - 20&oldid = 100471194


More articles:

  • Sony Ericsson Open 2010 - Men's Doubles
  • Earthquakes in the Solomon Islands (January 2010)
  • NGC 7233
  • Kariya Martin
  • Severyanskaya Dumka
  • NGC 7250
  • Osmanoglu, Ahmed Nihad
  • Pushkar
  • Karpilovka (Sumy region)
  • NGC 7269

All articles

Clever Geek | 2019